Supply-chain delays, rising equipment prices threaten electricity grid
The U.S. power grid is currently grappling with a significant crisis that extends beyond the mere need for additional power lines or generation sources. A striking example is the recent construction of two new data centers in Silicon Valley that remain idle due to the unavailability of essential electrical equipment, particularly transformers. These components are crucial for regulating voltage across the grid, and their scarcity highlights the broader supply chain issues affecting the entire electrical infrastructure. With an increasing demand for electricity driven by the electrification of appliances, a resurgence in domestic manufacturing, and the rapid growth of AI data centers, the need for transformers and other grid equipment has never been more pressing. However, the reality is that many existing transformers are aging, with over half of the approximately 60 to 80 million high-voltage distribution transformers in use exceeding their expected lifespan of 33 years.
The challenges facing the grid are exacerbated by severe supply chain bottlenecks, which have resulted in lead times for transformers reaching an astonishing 120 weeks, and up to 210 weeks for larger units. The production of these devices is heavily reliant on specific materials like grain-oriented electrical steel, predominantly sourced from a limited number of U.S. manufacturers, and imports from countries like Mexico and China. The situation is further complicated by the logistical challenges of transporting these heavy components, which can weigh between 100 and 400 tons and require specialized transport methods. The delays in procuring transformers and other necessary equipment, such as circuit breakers and high-voltage cables, have led utility companies to explore alternative solutions, including battery storage and the revival of decommissioned generation sites.
In response to these critical shortages, the Biden administration has taken steps to alleviate the situation, including delaying new energy-efficiency regulations for transformers and providing substantial funding to upgrade domestic steel production. However, experts acknowledge that these measures are only medium-term fixes. To truly address the underlying supply chain issues and enhance the reliability of the power grid, large-scale government incentives and a concerted effort to expand domestic production capabilities are essential. As utilities continue to navigate these challenges, the focus remains on innovative strategies to manage electricity demand and optimize existing resources, illustrating the complex dance required to maintain grid reliability amidst a backdrop of increasing energy needs.
https://www.youtube.com/watch?v=0UOxXzlHeJA
High-voltage power lines run through an electrical substation in Florida.
Joe Raedle/Getty Images
Two new data centers in Silicon Valley have been built but canβt begin processing information:
The equipment that would supply them with electricity
isnβt available.
Itβs just one example of a crisis facing the U.S. power grid that canβt be solved simply by building more power lines, approving new power generation, or changing out grid software. The equipment needed to keep the grid running β transformers that regulate voltage, circuit breakers that protect against faults, high-voltage cables that carry power across regions, and steel poles that hold the network together β is hard to make, and materials are limited. Supply-chain bottlenecks are taking years to clear, delaying projects, inflating costs and threatening reliability.
Meanwhile, U.S. electricity demand is surging from several sources β
electrification
of home and business appliances and equipment,
increased domestic manufacturing
and
growth in AI data centers
. Without the right equipment, these efforts may take years longer and cost vast sums more than planners expect.
Not enough transformers to replace aging units
Transformers are key to the electricity grid: They regulate voltage as power travels across the wires, increasing voltage for more efficient long-distance transmission, and decreasing it for medium-distance travel and again for delivery to buildings.
The
National Renewable Energy Laboratory
estimates that the U.S. has about 60 million to 80 million high-voltage distribution transformers in service. More than half of them are
over 33 years old
β approaching or exceeding their expected lifespans.
Replacing them has become costly and time-consuming, with utilities reporting that transformers cost
four to six times what they cost before 2022
, in addition to the multiyear wait times.
To meet rising electricity demand, the country will need many more of them β
perhaps twice as many as already exist
.
Even smaller transformers like these are in high demand and short supply.
AP Photo/Mel Evans
The
North American Electric Reliability Corporation
says the lead time, the wait between placing an order and the product being delivered, hit roughly 120 weeks β more than two years β in 2024, with large power transformers taking as long as 210 weeks β up to four years. Even smaller transformers used to reduce voltage for distribution to homes and businesses are
back-ordered as much as two years
. Those delays have slowed both maintenance and new construction across much of the grid.
Transformer production depends heavily on a handful of materials and suppliers. The cores of most U.S transformers use
grain-oriented electrical steel
, a special type of steel with particular magnetic properties, which is made domestically only by
Cleveland-Cliffs
at plants in Pennsylvania and Ohio. Imports have long filled the gap: Roughly
80% of large transformers
have historically been imported from Mexico, China and Thailand. But
global demand has also surged
, tightening access to steel, as well as copper, a soft metal that conducts electricity well and is crucial in wiring.
In partial recognition of these shortages, in April 2024, the U.S. Department of Energy
delayed the enforcement of new energy-efficiency rules
for transformers, to avoid making the situation worse.
Further slowing progress, these items cannot be mass-produced. They must be
designed, tested and certified individually
.
Even when units are built, getting them to where they are needed can be a feat. Large power transformers often weigh between 100 tons and 400 tons and require specialized transport β sometimes needing one of only about 10 suitable
super-heavy-load railcars
in the country. Those logistics alone can add months to a replacement project, according to the
Department of Energy
.
Enormous railcars like this one in Germany are often needed to transport high-voltage transformers from where they are manufactured to where they are used.
Raimond Spekking via Wikimedia Commons
,
CC BY-SA
Other key equipment
Transformers are not the only grid machinery facing delays. A Duke University Nicholas Institute study, citing data from research and consulting firm Wood Mackenzie, shows that
high-voltage circuit-breaker lead times
reached about 151 weeks β nearly three years β by late 2023, roughly double pre-pandemic norms.
Facing similar delays are a
range of equipment types
, such as transmission cables that can handle high voltages, switchgear β a technical category that includes switches, circuit breakers and fuses β and insulators to keep electricity from going where it would be dangerous.
For transmission projects, equipment delays can derail timelines. High-voltage direct-current cables now take more than 24 months to procure, and offshore wind projects are particularly strained: Orders for undersea cables can
take more than a decade to fill
. And fewer than
50 cable-laying vessels
operate worldwide, limiting how quickly manufacturers can install them, even once they are manufactured.
Supply-chain strains are hitting even the workhorse of the power grid: natural gas turbines. Manufacturers including Siemens Energy and GE Vernova have multiyear backlogs as
new data centers, industrial electrification and peaking-capacity projects
flood the order books. Siemens recently reported a record
US$158 billion backlog
, with some turbine frames sold out for as long as seven years.
The Cleveland-Cliffs steelworks in Ohio makes a specialized type of steel that is crucial for making transformers.
AP Photo/Sue Ogrocki
Alternate approaches
As a result of these delays, utility companies are finding other ways to meet demand, such as battery storage, actively managing electricity demand,
upgrading existing equipment
to produce more power, or even reviving decommissioned generation sites.
Some utilities are
stockpiling materials for their own use
or to sell to other companies, which can shrink delays from years to weeks.
There have been various other efforts, too. In addition to
delaying transformer efficiency requirements
, the Biden administration awarded
Cleveland-Cliffs $500 million
to upgrade its electrical-steel plants β but key elements of that grant were canceled by the Trump administration.
Utilities and industry groups are
exploring standardized designs and modular substations
to cut lead times β but acknowledge that those are
medium-term fixes
, not quick solutions.
Large government incentives, including grants, loans and guaranteed-purchase agreements, could help expand domestic production of these materials and supplies. But for now, the numbers remain stark: roughly 120 weeks for transformers, up to four years for large units, nearly three years for breakers and more than two years for high-voltage cable manufacturing. Until the underlying supply-chain choke points β steel, copper, insulation materials and heavy transport β expand meaningfully, utilities are managing reliability not through construction, but through choreography.
Kyri Baker receives funding from the U.S. Department of Energy, the National Science Foundation, and The Climate Innovation Collaboratory. She is a visiting researcher at Google DeepMind. The views and opinions expressed in this article are solely those of the author and do not necessarily reflect the views of the authorβs employer or any affiliated organizations.